The Sensible Project Manager Podcast
CAPM07 | Project Cost Management Part 2 Earned Value - Preparing for the CAPM
Terri Echegoyen and Mark Phillipy continue to study for the CAPM exam. In this session we cover the last section of Chapter 7 Project Cost Management of the PMBOK. The real highlight of the session is focused on learning about Earned Value. This is the seventh session in the mentoring series “Preparing for the CAPM”. Mark and Terri study together out of the fifth edition of the PMBOK as Terri gets ready to take the CAPM exam.
If you are new to project management or you are preparing to take the CAPM or PMP exam, grab your PMBOK and follow along. If you missed the first session, go back and start with the first in the series CAPM01 Introduction to Project Management.
Listen to the Podcast
During the podcast you will learn about the following Cost Management Process:
- Control Costs
However, within this process the main focus is on the Earned Value tools and techniques which include:
- Earned Value Management
- Planned Value (PV)
- Earned Value (EV)
- Actual Cost (AC)
- Schedule Variance (SV)
- Cost Variance (CV)
- Schedule Performance Index (SPI)
- Cost Performance Index (CPI)
- Forecasting
- Estimate At Completion (EAC)
- Budget At Completion (BAC)
- To-Complete Performance Index (TCPI)
- Performance Reviews
- Variance analysis
- Trend analysis
- Earned value performance
Earned Value Summary
To summarize the Earned Value Calculations refer to the table below. Note that this table was adapted from the Earned Value Calculations Summary Table located on page 224 of the 5th edition of the PMBOK.
Earned Value Calculations
Earned Value Dimensions
Abbreviation
Name
Equation
Meaning of Results
PV
Planned Value
EV
Earned Value
AC
Actual Cost
BAC
Budget At Completion
Variance Indicators
Abbreviation
Name
Equation
Meaning of Results
CV
Cost Variance
CV = EV – AC
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
SV
Scheduled Variance
SV = EV – PV
Positive = Ahead of Schedule
Neutral = On Schedule
Negative = Behind Schedule
VAC
Variance At Completion
VAC = BAC – EAC
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
Index Indicators
Abbreviation
Name
Equation
Meaning of Results
CPI
Cost Performance Index
CPI = EV / AC
Greater than 1.0 = Under planned cost
Exactly 1.0 = On planned cost
Less than 1.0 = Over planned cost
SPI
Schedule Performance Index
SPI = EV / PV
Greater than 1.0 = Ahead of Schedule
Exactly 1.0 = On Schedule
Less than 1.0 = Over planned cost
Forecasting Indicators
Abbreviation
Name
Equation
Meaning of Results
EAC
Estimate At Completion
EAC = BAC / CPI
EAC = AC + BAC – EV
EAC = AC + Bottom-up ETC
EAC = AC + [(BAC – EV)] / (CPI x SPI)]
ETC
Estimate To Complete
ETC = EAC – AC
TCPI
To-Complete Performance Index
TCPI = (BAC – EV) / (BAC – AC)
TCPI = (BAC – EV) / (EAC – AC)
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
Share with your friends
If you are enjoying this series and it is helping you prepare for either the CAPM or PMP exam I would ask that you please share this with a coworker or friend. I am very interested in sharing this series with as many project managers as possible.
Thank you for sharing!
Comments
I would appreciate it if you would leave a comment below regarding your experience in preparing for either the CAPM or PMP exam. If you have tips for others on how to prepare for the test, I am sure others would appreciate the suggestions.
To Subscribe to the Podcast
Click Here to Subscribe to via iTunes
I would love it if you could leave me an honest rating and review on iTunes by clicking here. Your review will help the show and its ranking in iTunes. Thank you!
Download Terri’s Study Spreadsheet!
To get a copy of Terri’s “Geeky” study spreadsheet, complete the signup form below.
(function(d, s, id) {
var js, fjs = d.getElementsByTagName(s)[0];
if (d.getElementById(id)) return;
js = d.createElement(s); js.id = id;
js.src = "http://forms.aweber.com/form/87/853205687.js";
fjs.parentNode.insertBefore(js, fjs);
}(document, "script", "aweber-wjs-iprkjhnml"));